1 |
Providing & Laying 200 mm to
1100 mm nominal dia Internal and
Peripheral Sewer Line in Ranhola
Group of Colonies under Nilothi
catchment area in Delhi. |
Executive Engineer (C)
DR-XII
Delhi Jal Board,
Pitampura, Delhi |
177.13 |
Work Just
awarded |
|
2 |
Providing Sewerage System in
Civic Amenities & Infrastructure
Deficient Area and other Approved
Area including Construction of
STP,MPS& IPS at Rohtak Town
under AMRUT |
Municipal Corporation,
Rohtak, Haryana |
193.23 |
Work in
progress |
|
3 |
Augmentation of sewerage net
work in deficit area including all
ancillary works, Reuse of treated
waste water along with O&M for 5
years in Sonepat Town under
AMRUT Program |
Municipal Corporation,
Railway Road,
Sonepat, Haryana |
114.60 |
Work in
progress |
|
4 |
Construction of Sewerage System
including ancillary works, IPS
along with O&M of the entire
system for 6 years (including one
year DLP) in Karnal Town. |
TATA Projects Ltd.,
H.No.1-7-80 to 87, Opp:
Wesley Co-ed
Jr.College, Prenderghast
Road, SECUNDERABAD500003 |
114.21 |
Work in
progress |
|
5 |
Development of DungargarhSardarshahar-Rajgarh Road from
Km 71/00 to 133/00 (S.H.-06). |
RSRDC Ltd., Unit
Bikaner 24-A, Nagnechi
Ji Scheme, Pawanpuri,
Bikaner |
96.12 |
Work in
progress |
|
6 |
Construction of two numbers of
vehicular half underpasses
between Wazirabad & Jagatpur
and one number pedestrian
subway near Gandhi Vihar on
Outer Ring Road, Delhi |
Executive Engineer, F11, PWD, Mukarba
Chowk, Delhi |
31.42 |
Work in
progress |
|
7 |
Earthwork, Flexible pavement,
River training & other protective
works at Wazirabad Signature
Bridge Project. |
Gammon India Ltd,
Gammon House, Veer
Savarkar Marg,
Prabhadevi, Mumbai |
100.60 |
18.08.2016 |
|
8 |
Providing and laying 280 to 1000
mm nominal dia internal and
peripheral sewer lines in Budh
Vihar group of colonies falling
under Rithala & Rohini WWTPS
catchment areas in Delhi. |
Executive Engineer (PR)
SR-I
Delhi Jal Board,
Sector-06, Rohini, Delhi110085 |
85.26 |
Work in
progress |
|
9 |
Supply of RMC for DMRC Contract
CC-26R. |
ITD-ITD CEM JV
301-302, Sagar Tower,
District Centre, Janak
Puri, New Delhi-110058 |
75.00
[approx.] |
Physically
completed |
|
10 |
Providing in position ready mixed
cement concrete, as per approved
design mix at DMRC CC-66 site. |
Hindustan Construction
Co. Ltd.
Hincon House, Vikhroli
(West), Mumbai |
75.00
[approx.] |
Physically
completed |
|
11 |
Providing and Transporting ready
mixed cement concrete, as per
approved design mix and at DMRC
CC30 Project site. |
Hindustan Construction
Co. Ltd.
Hincon House, Vikhroli
(West), Mumbai |
65.00
[approx.] |
Physically
completed |
|
12 |
Roadwork (Bituminous items) at
your PWD project, Namely,
“Comprehensive Development of
Corridor (Outer Ring Road)
between Mukarba Chowk to
Wazirabad Chowk. |
Continental Engineering
Corporation, 7th Floor,
Tower 7-B, Signature
Tower, Sec-29
NH-8, Gurgaon-122002
|
62.00 |
Physically
completed
|
|
13 |
Improvement including
Strengthening and Widening of
existing 2 lane Road to 4 lane Dual
Carriageway from Km 5.735 to Km
39.960 of NH-22 and km 0.00 to
km 0.870 of NH-21 (AmbalaChandigarh Section) in the states
of Haryana and Punjab Road
works.
|
GMR Projects Pvt. Ltd.,
9, King’s Street, Off
Richmond Road,
Bangalore -560025 |
52.96 |
30.09.2007 |
|
14 |
Road Widening Works, Bituminous
Work & other associated
Miscellaneous works for
Construction of Comprehensive
Development of Corridor between
Vikaspuri to Meerabagh Project for
M/s PWD, Delhi |
Simplex Infrastructures
Limited
Vaikunth, 2nd Floor,
82-83, Nehru Place,
New Delhi – 110 019. |
50.00
[approx.] |
21.07.2017 |
|
15 |
M/o various colonies Nazul A/c-II
in Dwarka. SH: Dense Bituminous
Carpeting on main Carriageway of
Master Plan Road of Dwarka. |
Executive
Engineer/SWD-7, Delhi
Development Authority,
Central Nursery, Sector5, Dwarka, New Delhi110075 |
40.69 |
16.06.2014 |
|
16 |
Covering of Drain passing through
Defence Colony from Ring Road to
Railway Line. |
Executive Engineer,
FOD-8, Delhi
Development Authority,
Aastha Kunj, Nehru
Place, New Delhi |
36.99 |
22.10.2014 |
|
17 |
Road work for Construction of
Bridge across River Yamuna near
Geeta Colony, Delhi. |
Navayuga Engineering
Co. Ltd., 48-9-17,
Dwarka Nagar,
Visakhapatnam(Andhra
Pradesh) |
34.90 |
22.12.2008 |
|
18 |
Providing park and ride and
holding facilities at Safdarjung
Airport (Commonwealth Games2010) |
Executive Engineer (RII), Civil Engineering
department, NDMC,
Tilak Lane, ND |
30.33 |
25.09.2010 |
|
19 |
Civil work at Green Park Metro
Station. |
Larsen & Toubro Ltd.,
Engg. Contract &
Construction Division,
211, Okhla Estate, |
27.49 |
31.03.2011 |
|
20 |
Contract BC-3:- Mass Earth filling
of Yamuna Depot at Yamuna
Khadir (Indraprastha – New Ashok
Nagar Corridor) for phase-II of
Delhi MRTS project. |
CE/Projects, DMRC Ltd.,
N.B.C.C. Place, Pragati
Vihar, New Delhi110003 |
26.65 |
15.05.2009 |
|
21 |
Civil work at Saket Metro Station. |
Larsen & Toubro Ltd.,
Engg. Contract &
Construction Division,
211, Okhla Estate |
26.21 |
31.05.2010 |
|
22 |
Mayur Vihar Link Road Project |
Noida Toll Bridge
Company Limited, Toll
Plaza, DND Flyway,
Opposite Sector 15-A,
Noida-201301(U.P.)
|
25.80 |
18.01.2008 |
|
23 |
Contract BC-31(D): Construction
of Staff Quarters at Sarita Vihar
Depot for Phase-II of Delhi MRTS
Project. |
Chief Project
Manager/South-East,
DMRC LTD., Lala Lajpat
Rai Marg, Lajpat NagarIV, New Delhi-110024 |
25.00 |
31.05.2012 |
|
24 |
Covering of Shahdra link drain in
front of Mayur Place Distt. Centre
(Phase-II work) RD-424 mtr. To
632 mtr. & RD-827 mtr. To RD
915. |
Executive Engineer, ED12, Delhi Development
Authority, Geeta Colony,
Delhi-110031 |
24.23 |
21.11.2012 |
|
25 |
Construction of Centre for Dental
Education & Research at AIIMS,
New Delhi. |
ADM(DZ), NBCC Ltd.,
NBCC Place, Pragati
Vihar, Bhisham Pitamah
Marg, New Delhi
110003. |
22.46 |
31.03.2007 |
|
26 |
Widening of Marginal Bund Road
from ITO Chungi Junction to Old
Yamuna Bridge from 4 Lane to 8
Lanes. |
Executive Engineer,
PWD Divn.-23(DS), 2nd
Nizamuddin Bridge,
Eastern Approach, NH24 By pass,Delhi-92 |
21.54 |
30.09.2006 |
|
27 |
Construction of 76 officers flats at
Sector-62, Noida civil, Internal &
External Water Supply, Complete
Sanitary Including External
Development Works for State
Bank of India officer’s flats. |
AGM, Premises & Estate
Department,
State Bank of India,
5th Floor, 11, Sansad
Marg, New Delhi110001 |
20.80 |
23.01.2016 |
|
28 |
Road Widening Works, Bituminous
Work & other associated
Miscellaneous works for
Construction of Comprehensive
Development of Corridor between
PrembariPul to Azadpur for M/s
PWD, Delhi. |
Simplex Infrastructures
Limited
Vaikunth, 2nd Floor,
82-83, Nehru Place,
New Delhi – 110 019. |
16.67 |
25.01.2016 |
|
29 |
Construction of main carriage way
(Two lanes) of 30 mt right of way
roads (cement concrete
pavement) in sector 34-35, Rohini |
Executive Engineer,
RPD-4,Delhi
Development Authority,
Rohini, Delhi-110085 |
16.55 |
Physically
completed |
|
30 |
Contract BC-31B: Construction of
Boundary Wall of Sarita Vihar
Depot for Phase-II of Delhi MRTS
Project. |
Dy. Chief Engineer/S.V.
Depot, DMRC LTD ,
Office of the CPM/SE,
Lala Lajpat Rai Marg,
Lajpat Nagar-IV, New
Delhi-110024 |
16.38 |
15.11.2010 |
|
31 |
"Utility Diversion work at Sikandra
Road" (Delhi)
|
Larsen & Toubro Ltd.,
Engg. Contract &
Construction Division,
211, Okhla Estate, Ph.-
III, New Delhi-20 |
16.00 |
30.09.2006 |
|
32 |
Construction of R.C.C. SW drains
& culverts in sector-26, Dwarka,
Phase-II |
Ex. Engr., WD-3, DDA
Lakkar Mandi, Kirti Nagar,
New Delhi-15 |
15.32 |
06.07.2015 |
|
33 |
Architectural Finishing Work
(General) at Three stations (Mayur
Vihar Phase-I, Mayur Vihar PhaseI Extn., New Ashok Nagar Station)
on Indraprastha – New Ashok
Nagar Corridor of Phase-II of Delhi
MRTS (Contract BA-6G) |
Dy. CPM/IN, DMRC Ltd.,
Site Office of Chief
Project Manager/East,
Seed
Bed Park, Shakarpur,
Delhi-110092 |
14.55 |
15.12.2009 |
|
34 |
Contract CC-39: Construction of
boundary wall and land
development of Bahadurgarh
Depot on Mundka – Bahadurgarh
Corridor of Phase-III Delhi MRTS. |
CPM/9
Delhi Metro Rail
Corporation Ltd.
25, Ashoka Road,
New Delhi-110001 |
14.36 |
30.06.2016 |
|
35 |
Strengthening of Road No. 17
(Nelson Mandela Marg) from Tpoint Baba Gang Nath marg to Tpoint Mehrauli Mahipalpur Road
and Mathura Road from Bhogal
ROB to Neela Gumbad, New Delhi.
|
Executive Engineer
PWD Division M112(GNCTD),
Shambhudayal Bagh,
Okhla Indl. Area-3, New
Delhi |
12.81 |
30.09.2010 |
|
36 |
Providing & laying og 150mm,
250mm, 600mm, 900mm,
1200mm, 2400mm dia sewer,
water & SWD lines at ITO to Delhi
Fate DMRC Stations. |
Metro Tunnelling DelhiL&T SUCG JV, DMRC
CC-05Project, CAG Park,
ITO, New Delhi-110002 |
12.17 |
31.03.2015 |
|
37 |
Contract CC-75: Construction of
Boundary Wall, Road and Allied
Works at Mundka Casting Yard of
Phase-III of Delhi MRTS |
Project Manager/SQ-1,
DMRC LTD., |
12.05 |
25.12.2015 |
|
38 |
Development of 443.44 hectare of
land in Phase-V, Sector 34 - 35,
Rohini. Sub Head : Providing and
laying Peripheral Water Supply
lines of Sector 34 & 35, Rohini |
Executive Engineer,
RPD-4,Delhi
Development Authority,
Rohini, Delhi-110085 |
11.61 |
05.10.2015 |
|
39 |
Diversion of 600mm, 900mm &
1100 mm dia Sewer lines including
extra work on Najafgarh (Shivaji)
Road at DMRC CC66 Project |
Hindustan Construction
Co. Ltd, Near District
health Centre, Delhi
Gate, Najafgarh, New
Delhi
|
12.43 |
31.07.2016 |
|